Centre allots Rs 3112 cr for ECoR in
Rail Budget
The Centre has allotted Rs 3112.48
crore for the East Coast Railway (ECoR).
Railway projects
in Odisha
SL
No
|
Name
of project
|
Budget
allotted (in crores)
|
01
|
Angul-Sukinda
New line, 98.7 km
|
75.00
|
02
|
Daitari-Bansapani
New Line, 185 km
|
12.00
|
03
|
Haridaspur-Paradeep
New Line, 82 km
|
36.8
|
04
|
Khurda
Road-Bolangir, 289 km
|
195.00
|
05
|
Lanjigarh-Junagarh,
|
7.50
|
06
|
Talcher-Bimalagarh
|
280.00
|
07
|
Jharsuguda-Rengali
Doubling
|
31.00
|
08
|
Sambalpur-Rengali
Doubling
|
2.60
|
09
|
Khurda
Road-Barang 3rd line
|
32.00
|
10
|
Cuttack-Barang
|
4.00
|
11
|
Sambalpur-Talcher
Doubling
|
97.00
|
12
|
Delang-Puri
Doubling
|
100.00
|
13
|
Sambalpur-Titilagarh
Doubling
|
470.00
|
14
|
Raipur-Titilagarh
|
241.52
|
15
|
Bansapani-Jakhapura
|
513.00
|
16
|
Brundamal-Jharsugura
Fly Over connection for joining down line
|
11.00
|
17
|
Barang-Rajathagarh
Doubling
|
16.00
|
18
|
Bhadrak-Nirgundih
3rd Line
|
125.00
|
Total
|
2249.42
|
|
New
Works
|
||
01
|
Vizianagaram-Samalpur
|
58.31
|
02
|
Jharapada-Budhapank
3rd & 4th line
|
45.73
|
03
|
Budhapank-Salegaon
3rd & 4th Line
|
34.30
|
04
|
Bhadrak-Vizianagaram
3rd line
|
120.05
|
05
|
Koraput-Singapur
Road
|
37.50
|
06
|
Khurda-Vizianagaram
Bye Pass
|
2.29
|
Total
|
298.18
|
|
Grand Total
|
2548.22
|
|
(A) Total Plan Outlay of ECoR
|
1576.01
|
|
(B) Extra Budget Resources
|
1536.47
|
|
Total Plan Outlay inclusive EBR (A+B) for ECoR
|
3112.48
|